Lexx-Connect has announced some news updates for Q2 2024.
Beginning with the new property tax rate at EXX is 0.64%.
Other items include:
- The beginning of work on the punch list for the ramp rehabilitation project. 
- Construction of the new 10,000 sq. ft. Corporate Hangar #1 began on April 1, 2024, with completion expected in November 2024. 
- Site prep work on the new 50,000 sq. ft. maintenance hangar on the north site and north ramp will begin shortly. 
- The AWOS will be relocated next to the glide slope antenna. 
- Construction of a storage unit for the airport's groundskeeping equipment will begin on the Green Needles side. 
- Total aircraft movements in April were 3,337. 